312-76 EC-Council Disaster Recovery Professional (EDRP)

What is Disaster Recovery?
Disaster recovery is the process, policies, and procedures related to preparing for recovery or continuation of technology infrastructure critical to an organization after a natural or human-induced disaster. Disaster recovery is a subset of business continuity. While business continuity involves planning for keeping all aspects of a business functioning in the midst of disruptive events, disaster recovery focuses on the IT or technology systems that support business functions.
Become a Certified Disaster Recovery Professional

This certification requires the following knowledge and skills:
Working knowledge of all areas of the organization and the ability to develop a clear understanding of the company’s key functional processes and resources.
Thorough knowledge and understanding of current disaster recovery planning techniques and technologies as well as the methods used in performing risk analyses and business impact analyses.
Working knowledge of data processing in order to assist in the preparation of recovery procedures in this area.
Working knowledge of data and voice telecommunications in order to assist in the preparation of recovery procedures in this area.
Good project management skills.
Ability to plan, organize, and direct the testing of emergency response, recovery support, and business resumption procedures.
Strong interpersonal skills to interface with managers and staff at all levels within the organization and to deal with vendors of record storage facilities and disaster recovery services.

Good oral and written communication skills.
Certification Target Audience
The EDRP certification is ideal for:
Network server administrators
Firewall Administrators
Security Testers
System Administrators

Risk Assessment professionals
Exam Information

EDRP (Prefix 312-76) exam is available at the ECC Exam Center.
EC-Council reserves the right to revoke the certification status of candidates that do not comply with all EC-Council examination policies found here.
EDRP Exam Details
Duration 4 Hours
Questions 150
EDRP Blueprint
Clause: Age Requirements and Policies Concerning Minors

The age requirement for attending the training or attempting the exam is restricted to any candidate that is at least 18 years old.
If the candidate is under the age of 18, they are not eligible to attend the official training or eligible to attempt the certification exam unless they provide the accredited training center/EC-Council a written consent of their parent/legal guardian and a supporting letter from their institution of higher learning. Only applicants from nationally accredited institution of higher learning shall be considered.

Disclaimer: EC-Council reserves the right to impose additional restriction to comply with the policy. Failure to act in accordance with this clause shall render the authorized training center in violation of their agreement with EC-Council. EC-Council reserves the right to revoke the certification of any person in breach of this requirement.

QUESTION 1
Which of the following tools in Helix Windows Live is used to reveal the database password of password protected MDB files created using Microsoft Access or with Jet Database Engine?

A. Asterisk logger
B. FAU
C. Access Pass View
D. Galleta

Answer: C

Explanation:

QUESTION 2
Mark is the project manager of the HAR Project. The project is scheduled to last for eighteen
months and six months already passed. Management asks Mark that how often the project team is
participating in the risk reassessment of this project. What should Mark tell management if he is
following the best practices for risk management?

A. At every status meeting of the project team, project risk management is an agenda item.
B. Project risk management happens at every milestone.
C. Project risk management has been concluded with the project planning.
D. Project risk management is scheduled for every month in the 18-month project.

Answer: A

Explanation:

QUESTION 3
You work as a project manager for TYU project. You are planning for risk mitigation. You need to identify the risks that will need a more in-depth analysis. Which of the following activities will help you in this?

A. Quantitative analysis
B. Estimate activity duration
C. Risk identification
D. Qualitative analysis

Answer: D
Explanation:

QUESTION 4
Della works as a security manager for SoftTech Inc. She is training some of the newly recruited
personnel in the field of security management. She is giving a tutorial on DRP. She explains that
the major goal of a disaster recovery plan is to provide an organized way to make decisions if a
disruptive event occurs and asks for the other objectives of the DRP. If you are among some of
the newly recruited personnel in SoftTech Inc, what will be your answer for her question?
Each correct answer represents a part of the solution. Choose three.

A. Guarantee the reliability of standby systems through testing and simulation.
B. Protect an organization from major computer services failure.
C. Minimize the risk to the organization from delays in providing services.
D. Maximize the decision-making required by personnel during a disaster.

Answer: A,B,C
Explanation:

QUESTION 5
Which of the following BCP teams is the first responder and deals with the immediate effects of the disaster?

A. Emergency management team
B. Damage assessment team
C. Off-site storage team
D. Emergency action team

Answer: D
Explanation:

 

Click here to view complete Q&A of 312-76 exam
Certkingdom Review
, Certkingdom PDF Torrents

MCTS Training, MCITP Trainnig

Best EC-Council Disaster 312-76 Certification, EC-Council Disaster 312-76 Training at certkingdom.com

312-76 EC-Council Disaster Recovery Professional (EDRP)
Scroll to top